Revised administrative sanction for HNSS Phase-II Package No.2 works
G.O.Rt.No.554, dated 28 Sep 2026, Water Resources Department
This GO gives revised administrative sanction of Rs.337.90 Crores for HNSS Phase-II Package No.2, covering canal lining from Km 260.000 to Km 300.000 including the tunnel.
Key points
- Revised administrative sanction is Rs.337.90 Crores for HNSS Phase-II Package No.2.
- The revised sanction is against the original Administrative Sanction of Rs.158.19 Crores.
- The work covers HNSS Main canal lining from Km 260.000 to Km 300.000, including the tunnel.
- The Chief Engineer must ensure correctness of provisions and rates, and Price Adjustment must follow the agreement/GO’s calculations.
- The Engineer-in-Chief and Chief Engineer must take further necessary action accordingly.
Who it applies to
- Engineer-in-Chief (AW/IW), A.P., Vijayawada
- Chief Engineer (Projects), Ananthapuramu
What changed?
The original administrative sanction for the three listed works was Rs.158.19 Crores; this GO revises the administrative sanction for the Package No.2 work to Rs.337.90 Crores.
Important conditions
- The Chief Engineer (Projects), Ananthapuramu shall ensure the correctness of the provisions, rates, statutory provisions and LS provisions proposed.
- Price Adjustment shall be arrived at based on the calculations stipulated in the agreement/GO’s.
- The expenditure shall be debitable to the Head of Account: MH 4700 - COL - Major and Medium Irrigation (01) Major Irrigation –MH - 137-HNSS - GH11 –State Development Schemes -SH -27 -Canal and distributaries -530 - Major Works / 531.
- The Engineer-in-Chief (AW/IW), A.P., Vijayawada and the Chief Engineer (Projects), Ananthapuramu shall take further necessary action accordingly.
Important dates
- 28 Sep 2026GO issued
- 17 Aug 2026Finance Department concurrence
What does this GO mean?
Our plain-language explanation. It is not the official wording.
This GO revises the administrative sanction for the HNSS Project Phase-II Package No.2 work covering lining of the HNSS Main canal from Km 260.000 to Km 300.000, including the tunnel from Km 285.100 to Km 287.100 in Ananthapuramu and Sri Satya Sai District.
The earlier administrative sanction for the three listed works was Rs.158.19 Crores. A revised estimate of Rs.339,50,00,000/- was submitted, and this GO accords revised administrative sanction of Rs.337.90 Crores for the Package No.2 work.
The Chief Engineer (Projects), Ananthapuramu is required to ensure the correctness of the provisions and rates, including statutory and LS provisions. Price Adjustment must be arrived at based on the calculations stipulated in the agreement/GO’s.
The expenditure is to be debitable to the specified Head of Account. The Engineer-in-Chief (AW/IW), A.P., Vijayawada and the Chief Engineer (Projects), Ananthapuramu are directed to take further necessary action. The order has the concurrence of Finance Department dated 17-08-2026.
The original order
G.O.Rt.No.554
Dated 28 Sep 2026
- Department
- Water Resources
- Issued by
- SHASHI BHUSHAN KUMAR, SPECIAL CHIEF SECRETARY TO GOVERNMENT
Subject, as printed
Water Resources Department - HNSS Project - Phase-II - Lining of HNSS Main canal from Km 260.000 to Km 300.000 including tunnel from Km 285.100 to Km 287.100 in Ananthapuramu and Sri Satya Sai District (Package No.2) – Revised Administrative Sanction – Accorded – Orders – Issued.